US 395 Widening Phase 1 Construction Alert

June 27, 2019
read adjacent text for details

As the San Bernardino County Transportation Authority (SBCTA) begins the US 395 – Phase 1 Widening Project, crews will place K-rail (temporary concrete barriers) along the five-mile corridor June 27-28 and July 1-3.

WHEN: June 27-28 and July 1-3

HOURS: Nighttime 9:00 p.m. to 6:00 a.m.

WHERE: Northbound (NB) and southbound (SB) US 395 between Chamberlaine Way and Palmdale Road (SR 18).

WORK: Placing K-rail (temporary concrete barriers).

CLOSURES: At least one lane will be open at all times in the four-lane section of US 395. One-way traffic control with flaggers will be required in the two-lane section of the highway. Expect delays and drive cautiously.

CHP will be onsite during closures. Please remember all construction is dynamic and the schedule is weather-permitting and subject to change.

To receive more information about the project and future construction, please sign up here.